Case Study: Recovery of BBJ Maintenance Project
Client Overview: The owner of a Boeing Business Jet (BBJ) signed a maintenance agreement with a reputable facility for a comprehensive inspection and repair project. Initially quoted at $750,000 (with $450,000 for the work order and $300,000 for defect rectifications), the project quickly escalated. As work began, the maintenance facility repeatedly requested advance payments, and the total costs ballooned to $1.8 million—while the aircraft was only halfway through its maintenance.
Challenge: Contracts were already in place, and the aircraft was already halfway through the required maintenance. Facing mounting costs, stalled progress, and little transparency, Vertex MXX stepped in to help bring the project back on track, renegotiating contracts, ensuring it stayed within budget, reducing downtime, and ensuring that only necessary work was performed.
Our Approach
Contract Review
Vertex MXX immediately reviewed the existing maintenance agreement, identifying areas where the owner’s interests were inadequately protected. We analysed discrepancies between the original work quote and the excessive invoices, highlighting inflated costs and potential inconsistencies.On-Site Engineers and Audit
To gain a comprehensive understanding of the project status, we deployed two experienced engineers to the facility. They conducted a meticulous audit of the work completed to date, assessed the quality of repairs, and verified whether unnecessary repairs had been conducted or billed, ensuring complete transparency.Renegotiation and Project Management
Based on our findings, we initiated discussions with the maintenance facility to renegotiate terms for the remaining work. Our team took over project management to ensure that no further unnecessary costs were incurred, overseeing the completion of the project while safeguarding the owner’s interests.
The Results
USD 800,000 in Savings: Through rigorous oversight, renegotiation, and careful auditing, Vertex MXX managed to bring the final cost down by $800,000, significantly reducing the financial burden on the owner and aligning the costs more closely with the initial estimate.
Transparent Process: Vertex MXX ensured full transparency throughout the remaining work. All invoices were scrutinised to confirm they reflected only necessary repairs, giving the owner complete visibility into every stage of the project.
Swift and Efficient Completion: Under Vertex MXX’s management, the maintenance project moved forward efficiently, allowing the aircraft to be completed and returned to service on time without additional delays or cost overruns.
Why This Matters for You
By stepping in to manage this BBJ maintenance project, Vertex MXX turned a spiralling situation around, saving the owner a substantial $800,000 and completing the project within a controlled budget and timeframe. Our expertise in contract negotiation, project management, and on-site auditing provided the transparency and cost control needed to bring the project back on track.
Protect your investment with Vertex MXX. If you’re looking to avoid inflated costs and ensure efficient, transparent project management, contact us today to learn how we can support your next maintenance project.